clarify that NodeInfo/@XXXDuration includes weekends

    XMLWordPrintable

    Details

    • Type: Story
    • Status: Implemented (View Workflow)
    • Priority: Normal
    • Resolution: Fixed
    • Affects Version/s: None
    • Fix Version/s: 1.7, 2.1
    • Component/s: Resources
    • Labels:
      None
    • Draft:
      Hide

      Table 8.208: NodeInfo Resource

      CleanupDuration ... Estimated duration of the clean-up phase of the process. Note: @CleanupDuration includes non-working days such as weekends or holidays.

      <repeat appropriately for TotalDuration and SetupDuration>

      Show
      Table 8.208: NodeInfo Resource CleanupDuration ... Estimated duration of the clean-up phase of the process. Note: @CleanupDuration includes non-working days such as weekends or holidays. <repeat appropriately for TotalDuration and SetupDuration>

      Description

      when used for product scheduling, the # of days should include any weekend days rather than require knowledge of the working days

        Attachments

          Activity

            People

            • Assignee:
              Unassigned
              Reporter:
              prosi Rainer Prosi
            • Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

              Dates

              • Created:
                Updated:
                Resolved: